                      NOTICE
********************************************************

This document was converted from Microsoft Word.

Content from the original version of the document such as
headers, footers, footnotes, endnotes, graphics, and page numbers
will not show up in this text version.

All text attributes such as bold, italic, underlining, etc. from the
original document will not show up in this text version.

Features of the original document layout such as
columns, tables, line and letter spacing, pagination, and margins
will not be preserved in the text version.

If you need the complete document, download the
Microsoft Word or Adobe Acrobat version.

*****************************************************************




                           Before the
                Federal Communications Commission
                     Washington, D.C. 20554
                                
In the Matter of                 )    File No. EB-02-TC-060
                                )
CableOne                         )    CUID No.  CA0901 (Union 
                                )    City)                
Refund Plan                    ) )


                              ORDER

          Adopted:  September 4, 2002                  Released:  
September 6, 2002        

By the Chief, Enforcement Bureau:1

     1.    In this  Order we  consider the refund  plan filed  on 
August 20, 2002  by the  above-referenced operator  ("Operator")2 
pursuant to Order, DA 02-16963 ("Refund Order").4  Our review  of 
Operator's refund plan5 reveals that the refund plan fulfills the 
requirements of the Refund Order.     

     2. Accordingly, IT IS  ORDERED that  Operator's refund  plan 
IS APPROVED and IT IS FURTHER ORDERED, pursuant to Section 76.962 
of the  Commission's rules,  47 C.F.R.  § 76.962,  that  Operator 
implement its refund plan within 60  days of the release of  this 
Order.

     3. IT IS FURTHER ORDERED, pursuant to Section 76.962 of  the 
Commission's rules, 47 C.F.R. § 76.962, that Operator shall  file 
a certificate of compliance  with the Chief, Enforcement  Bureau, 
within 90  days  of the  release  of this  Order  certifying  its 
compliance with this Order.

     4. This action  is  taken  pursuant to  Sections  0.111  and 
0.311 of the Commission's rules, 47 C.F.R. §§ 0.111 and 0.311.
                    
                              FEDERAL COMMUNICATIONS COMMISSION 

                         
                              David H. Solomon
                              Chief, Enforcement Bureau
                         
_________________________

1  Effective   March  25,   2002,  the   Commission   transferred 
responsibility for resolving cable programming services tier rate 
complaints  from  the  former   Cable  Services  Bureau  to   the 
Enforcement Bureau.  See Establishment  of the Media Bureau,  the 
Wireline Competition  Bureau and  the Consumer  and  Governmental 
Affairs Bureau, Reorganization  of the  International Bureau  and 
Other Organizational Changes, FCC 02-10, 17 FCC Rcd 4672 (2002).
2  The  term  "Operator"  includes  Operator's  predecessors  and 
successors in interest.
3 In the Matter  of CableOne, DA 02-1696  (EB, released July  17, 
2002). 
4 The Refund Order required Operator to determine the overcharges 
to cable programming  service tier ("CPST")  subscribers for  the 
period stated in  the Refund  Order and  file a  report with  the 
Chief, Enforcement Bureau, stating  the cumulative refund  amount 
determined (including  franchise fees  and interest),  describing 
the calculation thereof, and describing its plan to implement the 
refund within 60 days of Commission approval of the plan.
5 Operator calculated a total refund liability of $41,246.61.