Click here for Adobe Acrobat version
Click here for Microsoft Word version
******************************************************** 
                      NOTICE
********************************************************

This document was converted from Microsoft Word.

Content from the original version of the document such as
headers, footers, footnotes, endnotes, graphics, and page numbers
will not show up in this text version.

All text attributes such as bold, italic, underlining, etc. from the
original document will not show up in this text version.

Features of the original document layout such as
columns, tables, line and letter spacing, pagination, and margins
will not be preserved in the text version.

If you need the complete document, download the
Microsoft Word or Adobe Acrobat version.

*****************************************************************




                                   Before the

                       Federal Communications Commission

                             Washington, D.C. 20554

   In the Matter of )

   )

   Raytheon ) File No. EB-11-LA-0207

   Antenna Structure )

   ASR # 1017658 ) NOV No. V201232900007

   Fullerton, CA )

   )

                              NOTICE OF VIOLATION

   Released: November 30, 2011

   By the District Director, Los Angeles District Office, Western Region,
   Enforcement Bureau:

    1. This is a Notice of Violation ("Notice") issued pursuant to Section
       1.89 of the Commission's Rules, to Raytheon concerning antenna
       structure # 1017658 in Fullerton, CA.

    2. On September 28, 2011, an agent of the Enforcement Bureau's Los
       Angeles Office inspected antenna structure # 1017658 located at 1801
       Hughes Dr., Fullerton, CA, and observed the following violations:

   a. 47 C.F.R. S: 17.57: "The owner of an antenna structure for which an
   Antenna Structure Registration Number has been obtained must notify the
   Commission within 24 hours of completion of construction (FCC Form 854-R)
   and/or the dismantlement (FCC Form 854). The owner must also immediately
   notify the Commission using FCC Form 854 upon any change in structure
   height or change in ownership information." At the time of the inspection
   on September 28, 2011, the FCC's antenna structure registration database
   had not been updated to show that antenna structure # 1017658 was owned by
   Raytheon.

   b. 47 C.F.R. S: 17.4(g): "The Antenna Structure Registration Number must
   be displayed in a conspicuous place so that it is readily visible near the
   base of the antenna structure. Materials used to display the Antenna
   Structure Registration Number must be weather-resistant and of sufficient
   size to be easily seen at the base of the antenna structure." At the time
   of inspection, the agent observed that there was no registration number
   posted at or near the base of the antenna structure.

    3. Pursuant to Section 403 of the Communications Act of 1934, as amended,
       and Section 1.89 of the Commission's Rules, Raytheon, must submit a
       written statement concerning this matter within 20 days of release of
       this Notice. The response must fully explain each violation, must
       contain a statement of the specific action(s) taken to correct each
       violation and preclude recurrence, and should include a time line for
       completion of pending corrective action(s). The response must be
       complete in itself and signed by a principal or officer of Raytheon.
       All replies and documentation sent in response to this Notice should
       be marked with the File No. and NOV No. specified above, and mailed to
       the following address:

   Federal Communications Commission

   Los Angeles Office

   18000 Studebaker Rd., Suite 660

   Cerritos, CA 90703

    4. This Notice shall be sent to Raytheon at its address of record.

    5. The Privacy Act of 1974 requires that we advise you that the
       Commission will use all relevant material information before it,
       including any information disclosed in your reply, to determine what,
       if any, enforcement action is required to ensure compliance. Any false
       statement made knowingly and willfully in reply to this Notice is
       punishable by fine or imprisonment under Title 18 of the U.S. Code.

   FEDERAL COMMUNICATIONS COMMISSION

   Nader Haghighat

   District Director

   Los Angeles District Office

   Western Region

   Enforcement Bureau

   47 C.F.R. S: 1.89.

   47 U.S.C. S: 403.

   P.L. 93-579, 5 U.S.C. S: 552a(e)(3).

   18 U.S.C. S: 1001 et seq.

   Federal Communications Commission

   2

                       Federal Communications Commission